Community and Business Units (The Space)
Proposal code: THC-2026-01-31
This project delivers ‘The Space’, a new multi-purpose building forming a critical part of our village Community Hub.
Estimated Price
667292
The project is to develop ‘The Space’ a 100 m2 multi-purpose, low energy building in the heart of Culbokie. It is part of a bigger Community Hub project being developed on land owned by the Culbokie Community Trust within the biodiverse setting of Culbokie Green. The Space will comprise:
- rental space for an anchor tenant,
- 2 community health rooms,
- meeting room with video conference facilities,
- flexible community space with up to four (removable) hot-desks.
Community Issues and Priorities
- The building seeks to address issues of:
- inequalities of access to services due to a very limited bus service and no local health provision;
- loss of young people from the area due to a lack of local business and employment opportunities
- a lack of community income and wealth generation to support long term growth, resilience and financial sustainability.
The specific priorities identified by the community during a community consultation in 2023 were the need for health services, some shop front space (for example, for a butcher, hairdresser or crafts), a digitally connected meeting room, office space and hotdesk/coworking space.
Project Aims
Reflecting these issues and priorities, three principle aims have been set for this project which will strengthen the economy and achieve a high level of social outcomes:
- To complete the construction of The Space, as an integrated part of the Community Hub, leading to the further transformation of Culbokie village centre from an abandoned field into a vibrant, attractive and biodiverse community facility supporting community wellbeing
- To provide critical local services and business opportunities with a priority on health and wellbeing, addressing disadvantage and environmental sustainability
- To generate the necessary income to secure the Hub's future.
We expect the project will also build further momentum to enable the development of the final component of the Hub - the community café.
All necessary permissions have been obtained for the construction of The Space (including planning consent and a building warrant). A fully documented open tender exercise earlier this year led to the selection of a preferred builder out of three bidders. The tender has since expired and will be refreshed should this funding be approved. A contingency to allow for an increase in prices has been added to the tender figure for the purposes of this application.
Dates: The proposed construction start date is May 2026 with a ready for occupancy date of June 2027.